Golden Sierra High School

Owner – Black Oak Mine Unified School District

Program/Project Management – Premier Management Group

Architect – ATI Architects

General Contractor – Landmark Construction

Project Budget – 9.5 million

Description – Golden Sierra High School’s new construction project included building a new wing which houses Drama, Music, and Science classes.  The project also included earthwork, site demolition and preparation, new and modified site sewer, site drainage, domestic water, and fire water, modifications to the existing leach field, handicap ramps, walk-in freezer and refrigerator, and new electrical main services.

Golden Sierra High School’s modernization project included modernization of the existing main building including new M.E.P systems to serve the need of new electrical systems, new finishes, new restrooms, new skylights, and kitchen modifications.